Hull jobs nearly finished
Friday 1 Nov, HHN day 21: Finishing touches on the antifouling, and more hoses get installed. Three weeks already since we landed back into USA, and we are still on the hard,…
Friday 1 Nov, HHN day 21: Finishing touches on the antifouling, and more hoses get installed. Three weeks already since we landed back into USA, and we are still on the hard,…
Thursday 31 Oct, HHN day 20: Last thru-hulls installed and functional galley sink at long last. Same as yesterday, we set a slightly earlier waking up alarm so that we make the…
Wednesday 30 Oct, HHN day 19: Hoses getting re-installed and A LOT of time again wasted on a faulty galley faucet and mission-impossible to reinstall. More dreams (or nightmares) about thru-hulls, valves,…
Tuesday 29 Oct, HHN day 18: And the work continues… Another day, another set of jobs. First thing we do when we get out of bed is check the backing plates, how…
Monday 28 Oct, HHN day 17: Finally, 5 new shiny sea-cocks are installed. Busy week ahead of us, and the priority is to make Cloudy Bay watertight again. 6 holes to fill,…
Sunday 27 Oct, HHN day 16: Sunday? Pffff, no day of rest for us! Painting the engine room and visit Fawcett. Not a good sleep last night for either of us. Wind…
Saturday 26 Oct, HHN day 15: More painting (hull and Glen) and more skin-fitting preps. Oh, and a nice dinner out for once. Today’s jobs start indoors, with yet more measuring, cutting…
Friday 25 Oct, HHN day 14: First day of antifouling. Quite a workout! Early start as we have a big day ahead of us, paint the antifouling. It’s the fourth time we…